| Description |
The purpose of this project was to compare the safety risks associated with completely removing 3 representative platforms from the POCSR. There were 2 phases:
|
| Progress | The forum of decommissioning safety was held in Ventura, CA on February 11-12, 2003 with invited experts on decommissioning. The attendees reviewed a draft interim report that lists the safety aspects of decommissioning Federal platforms offshore CA. A revised phase 2 report for the project was prepared. |
| Report | |
|
AA
(162 pages)
|
Twachtman Snyder & Byrd, Inc. Comparative Health and Safety Risk Assessment of Decommissioning Large Offshore Platforms, Final Report, Case Studies for Decommissioning of Three Offshore Platforms in the Pacific OCS Region, June 2003. |
|