| Project Number | 352 |
| Date of Summary | October 15, 2002 |
| Subject | Assessment of Current Pipeline Flushing and Decommissioning Requirements - Research and Field Testing (Flushing Phase A & B) |
| Performing Activity | WINMAR Inc. |
| Principal Investigator | James Wiseman |
| Contracting Agency | Minerals Management Service |
| Completion | Completed |
| Description | To assist MMS in scoping and preparing regulations for the flushing, handling, and future decommissioning of out-of-service pipelines. |
| Progress | Project is complete. |
Reports |
|
| AB (228 pages)
|
Assessment of Current Pipeline Flushing and Decommissioning Requirements - Research and Field Testing, Final Report, "Flushing Phase A", James Wiseman, WINMAR Consulting Services, March 25, 2001. |
|
AC (139 pages)
|
Assessment of Current Pipeline Flushing and Decommissioning Requirements - Research and Field Testing, Final Report, "Flushing Phase B", Chris Auer, WINMAR Consulting Services, September 26, 2002. |
|
Privacy | Disclaimers | Accessibility | Topic Index | FOIA Last Updated: 04/15/2008, 06:04 AM
|
|